Reference Projects

Over the years Proeco International d.o.o. achieved the following project references:


Year 2020/2021/2022 (ongoing projects):

  • Client KT – Kinetics Technology S.p.A. for INA Croatia (3.000 MNH)
    • On-site multidiscipline services: DCU Project (INA Rijeka Refinery)
      • n°1 HSE Engineer
      • n°1 QA/QC Engineer
      • n°12 Months job continuous duration (no rotation)
  • FATA S.p.A. (Gruppo Danieli) for HEP Croatia (5.600 MNH)
    • On-site multidiscipline services: KKE Power Plant Upgrade Project (EL-TO Zagreb)
      • n°1 Lead Mechanical Engineer
      • n°1 Lead Piping Engineer
      • n°2 Lead E&I Engineer
      • n°1 QA/QC Manager
      • n°9 Months job continuous duration (no rotation)

Other Design engineering activities:

  • PIPING DESIGN ENGINEERING for CHS, OSBL, Interconnecting Units using CADWorx software consisting of:
    • 3D model
    • Plot Plan issue
    • Layout issue
    • P&IDs update
    • Isometrics development
    • BOQ submission for piping
    • BOQ submission for piping supports
    • Firefighting modelling, isometrics and BOQ
    • Structure modelling, isometrics and BOQ
    • Database development and update
  • PIPING AND STRUCTURAL BID ENGINEERING (offshore skid mounted unit) consisting of:
    • Structure 3D model
    • BOQ submission for piping
    • BOQ submission for valves (including PSV, Control Valves and On/Off Valves)
    • BOQ submission for structures
  • STRUCTURE DETAIL DESIGN ENGINEERING consisting of:
    • 3D model update
    • Workshop documentation
    • BOQ submission

Year 2019/2020:

  • Client KT – Kinetics Technology S.p.A. for INA Croatia (6.000 MNH)
    • On-site multidiscipline services: PPS Project (INA Rijeka Refinery)
      • n°1 Field Engineer
      • n°4 Commissioning Engineers
      • n°16 Months job continuous duration (no rotation)
  • Client Scandiuzzi Steel Constructions S.p.A. for Borealis (2.500 MNH)
    • Office based design engineering services: Kallo Project (Belgium)
      • Pressure Vessels Detail Engineering
      • n°5 Design Engineers
      • n°6 Months job duration

Year 2017/2018:

  • Client CONSORZIO INIZIATIVE VAL D’AGRI for TOTAL E&P Italy (4.000 MNH)
    • On-site multidiscipline services: TEMPA ROSSA (Valle del Sauro – Basilicata – Italy)
      • n°2 Commissioning Engineers
      • n°10 Months job continuous duration (no rotation)
  • Client TOZZI EAST for STL-SOUTH TAMBEY LNG (10.000 MNH)
    • On-site multidiscipline Commissioning services YAMAL LNG PLANT (integrated project encompassing natural gas production, liquefaction and shipping.)
      • n°8 Commissioning Engineers
      • n°12 Months job with heavy duty rotation 28 / 28 (Arctic – Polar zone)

Year 2016:

  • Client TOZZI EAST for services on installation of instrumentation and electrical sensors on VOLGOGRAD DEEP CONVERSION PROJECT (Tacnicas Reunidas) (2.000 MNH)
    • n°2 Commissioning Engineers
    • n°8 Months job duration in continuous rotation 42 on / 15 off
  • Client TOZZI SUD S.p.A. for Supervision Multidiscipline services during construction and commissioning on A NEW BUILT BARGE FLOATING PRODUCTION UNIT (FPU) FOR THE JANGKRIK COMPLEX PROJECT DEVELOPMENT – SAIPEM KARIMUN for ENI Indonesia (6.000 MNH)

Year 2015:

  • Client SAIPEM for Shah Deniz II Project (BP) – Caspian Sea (2.000 MNH)
    • 2 Engineers/ Supervisor for Mechanical completion on DBA (Derrick Barge Azerbaijan):
      • n°1 Mechanical/Equipment Supervisor
      • n°1 E&I Supervisor
  • Client TOZZI SUD for Gas Shetland Plant (Petrofac) – North Sea Shetland island (10.000 MNH)
    • Engineers/ Supervisor for Mechanical completion and for Commissioning activities on 5.000 Instrumental Loops
      • n°10 Field Engineers and Supervisors
      • n°6 Months job duration in continuous rotation 42 on / 15 off

Year 2014:

  • Client INAgip … N°4 Multidiscipline supervisors in HOOK-UP Top Sides facilities on IKA JZ and IKA A for IKA JZ interconnecting development: PIPING, MECHANICAL, E&I, COORDINATION (3.600 MNH)
  • Client SAIPEM for Shah Deniz II Project (BP/SOCAR) – Caspian Sea (3.000 MNH):
    • 3 Engineers/ Supervisor for Multidiscipline engineering and Mechanical completion on PLBH (Pipe Layer Barge Huseinov):
      • n°1 Mechanical/Equipment supervisors
      • n°1 E&I supervisor
      • n°1 Pipe Layer barge Assistant to Superintendent

 Year 2013:

  • Client Proger/ENI for Kashagan D Island – Caspian Sea … 15 Multidiscipline Engineers/ Supervisor for Multidiscipline engineering and Mechanical completion (22.500 MNH):
      • n°4 Mechanical/Equipment supervisors
      • n°2 Piping supervisors
      • n°2 Electrical supervisors
      • n°4 Instrumental supervisors
      • n°3 NDT and HSE supervisors
  • Client PROECO srl for Val D’Agri ENI Oil field … Multidiscipline engineering development with Piping and E&I detail engineering (2.000 MNH)
  • Client PROECO srl for BONATTI … Piping and Instrumental detail engineering for Val D’Agri ENI Oil field (2.000 MNH)
  • Client INAgip (2013-2014)… N°10 Multidiscipline supervisors in Viktor Lenac yard on IKA JZ construction development: PIPING, STRUCTURAL, PAINTING, E&I (20.000 MNH)
  • Supervising on IKA JZ – Viktor Lenac yard

Year 2012:

  • Client SAIPEM SpA/ Proeco FWA/ for MAADIA Petrobel/Petrojet, Naval Architect Supervision for SETH platform towing & installation barge conversion/remake (1.000 MNH)
  • Client FORES Engineering (Rosetti Group) E&I Supervision for Electrical and Instrumental work completion on Petrobel SETH platform (2.000 MNH)
  • Client Rosetti Marino SpA for SFAX – Tunis –  ASHTART platform revamping … Multidiscipline ON-SITE yard engineering with mostly PIPING and STRUCTURE engineering details (1.000 MNH)
  • Client Rosetti Marino SpA for AKTAU – Kazakhstan … Engineering of Fuel Gas skid manifolds with PIPING and E&I detail development and 1 Commissioning Engineer Site supervision (2.000 MNH)
  • Client Tecnomare SpA for AKSAI – Kazakhstan … 1 Piping Project engineer and Supervisor on behalf Marine Caspian Services for Tecnomare (1.000 MNH)
  • Client SAIPEM S.p.A. for INAgip … Multidiscipline Basic engineering for revamping of Ivana B and Ika A platform for future IKA JZ platform installation included on-site pre engineering survey (1.000 MNH)